The Park Street exit ramp has closed.
The stairwell located by the current loading dock is being remodeled to direct users safely to the temporary loading dock and away from the main construction area. Faculty, staff and students are asked to avoid that area/stairwell (Park Street stairwell and current loading dock area) while work is underway. If you use that area to exit the building on foot, please use the University Avenue or Johnson Street exits instead. The old courtyard is being blacktopped in order to serve as the new loading dock for the next two years. Room 1250 (the old deli) will be the loading dock receiving area during this period.
Weekly email updates on the Grainger Hall Addition are being sent by Building Supervisor Cheryl Schroud. If you have not received these updates and would like to, please contact her at cschroud@bus.wisc.edu.