Latest Information on Grainger Hall Construction

June 1, 2008

To keep everyone in the Wisconsin School of Business community informed on progress on the construction of the east wing and the moves that will follow, an email reporting on construction/moving progress is being sent every Friday until the transition is complete.

The most current schedule is:

Moving to the 4th floor of the east wing – June 23

Moving to the 3rd floor of the east wing – June 24

Moving to the 2nd floor of the east wing – June 25

Carpet cleaning and painting of vacated spaces – Week of June 30

Moves to the vacated spaces Week of July 7 (tentative)

Any questions or concerns about construction and the moves, or suggestions for areas to be covered in future emails, should be sent to Melissa Amos-Landgraf mamos@bus.wisc.edu or Cheryl Schroud, cschroud@bus.wisc.edu.